Country : Australia
Assignment Task :

Project overview
In this assessment you will:

Produce a schedule of resource requirements for the King residence (workshop and garage) so that orders can be placed for materials and labour. 
Calculate costs for 6m x 7m workshop and garage for the King residence for concrete floor/slab, colourbond roof and external wall cladding.  
Show how material and labour costs will be recorded and tracked, including for a contract variation. 
Prepare/identify aspects required for a site file including: site plans, overlay drawings, specifications, contract and approvals, local government conditions of approval, details of suppliers and contractors, work and building schedule, labour and materials schedule (from above), call forward sheets.
Show your knowledge of codes, regulations and approval processes.
Project instructions
This project is broken into three parts: parts A, B and C. 
Overall you are required to submit material and labour resource schedulesusing the templates provided, as well as a site file list and documents. Your assessment should refer to relevant codes, regulations and approval processes.

Read the scenario below that relates to the building of the King’s residence workshop and garage, andcarry out the tasks that follow.

Scenario
Based on theKing plans – specifically the proposed garage and workshop area, you will take on the role of Jai, the Site Supervisor for Sullivon Constructions. Jai’s task in this case is to produce a series of schedules (including colour selections*), costs and site file documents that will be used in the construction of the project. 
Jai realises the client has changed their mind on the size of the shed after the plans have been submitted which now requires a variation to the contract and drawings. To get an accurate size on the new shed, Jainow needs to access the supply companies’ installation documents.
Jai needs to be carefulnot to miss-measure, the existing plans say 6m x 10m, however the actual shed will be 6m x 7m - everything else is the same.
*The King’s have requested that the workshop and garage colours match with the house colours: stone/beige external walls with charcoal trims.
You will also need to access relative codes or the NCC, to verify complianceas needed.
 


Part A - Resource schedules 
Produce resource schedules that Jai would create for the King residence as follows:
Produce schedules of resource requirements based on a contract for the King residence workshop and garage, as pictured below,so that orders can be placed for labour, equipment and materials. 
For the workshop and garage the client has chosen a Fair dinkum Shed. Use the link to access and download the installation guide, which includes the floor plan sizes to be used on p.45. 

 

This Building and Construction Assignment has been solved by our Building and Construction Experts at onlineassignmentbank. Our Assignment Writing Experts are efficient to provide a fresh solution to this question. We are serving more than 10000+ Students in Australia, UK & US by helping them to score HD in their academics. Our Experts are well trained to follow all marking rubrics & referencing style.

Be it a used or new solution, the quality of the work submitted by our assignment experts remains unhampered. You may continue to expect the same or even better quality with the used and new assignment solution files respectively. There’s one thing to be noticed that you could choose one between the two and acquire an HD either way. You could choose a new assignment solution file to get yourself an exclusive, plagiarism (with free Turnitin file), expert quality assignment or order an old solution file that was considered worthy of the highest distinction.

  • Uploaded By : admin
  • Posted on : July 20th, 2018
  • Downloads : 0

Whatsapp Tap to ChatGet instant assistance